Supply Chain Management

Supply chain management is a new concept of doing business, which has been recognized and practiced by the manufacturing industry for the last two decades. It has also emerged as new practice in construction industry.

Because of emerging technological advances and to maintain competitive advantage in business environment, it has become essential to plan, organize, and control

TABLE 1.14

Typical Categories of Risks in Oil and Gas Projects

Sr. No.

Category

Types

1

Management

Selection of project delivery and contracting system Selection of project management consultant

2

Contract (project)

Scope/design changes

Schedule

Cost

Conflict resolution

Delay in changer order negotiations

3

Statutory

Statutory/regulatory delay

4

Technical

Incomplete design Incomplete scope of work Design changes Design mistakes

Errors and omissions in contract documents Incomplete specifications Ambiguity in contract documents Inconsistency in contract documents Inappropriate schedule/plan Inappropriate construction method Conflict with different trades Improper coordination with regulatory authorities Inadequate site investigation data

5

Technology

New technology

6

Construction

Delay in mobilization Delay in transfer of site

Different site conditions to the information provided

Changes in scope of work

Resource (labor) low productivity

Equipment/plant productivity

Insufficient skilled workforce

Union and labor unrest

Failure/delay of machinery and equipment

Quality of material

Failure/delay of material delivery

Delay in approval of submittals

Extensive subcontracting

Subcontractor’s subcontractor

Failure of project team members to perform as expected Information flow breaks

TABLE 1.14 (Continued)

Typical Categories of Risks in Oil and Gas Projects

Sr. No.

Category

Types

7

Physical

Damage to equipment Structure collapse Damage to stored material Leakage of hazardous material Theft at site Fire at site

8

Logistic

Resources availability Spare parts availability Consistent fuel supply Transportation facility Access to worksite Unfamiliarity with local conditions

9

Health, safety, and environment

Injuries

Health and safety rules Environmental protection rules Pollution rules Disposal of waste

10

Financial

Inflation

Recession

Fluctuations in exchange rate

Availability of foreign exchange (certain countries)

Availability of funds

Delays in payment

Local taxes

11

Economical

Variation of construction material price Sanctions

12

Commercial

Import restrictions Custom duties

13

Legal

Permits and licenses Professional liability Litigation

14

Political

Change in laws and regulations

Constraints on employment of expatriate workforce

Use of local agent and firms

Civil unrest

War

15

Natural/environmental

Flood Earthquake Cyclone Sandstorm Landslide Heavy rains High humidity Fire

TABLE 1.14 (Continued)

Typical Categories of Risks in Oil and Gas Projects

Sr. No.

Category

Types

16

Geological

Estimation of accessible reserves

17

Supply and demand

Financial crises and macroeconomic factors

18

Operational

Availability of skilled workers

EPC, engineering, procurement, and construction.

Source: Abdul Razzak Rumane. (2013). Quality Tools for Managing Construction Projects. Reprinted with permission from Taylor & Francis Group.

TABLE 1.15

Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action

Sr. No.

Potential Risk

Probable Effects

Control Measures/Mitigation Action

1.0 Scope

l.l

Scope/design changes

  • • Project schedule
  • • Project cost
  • • Claim
  • • Compress schedule.
  • • Resolve change order issues in order not to delay the project.

1.2

Different site conditions to the information provided

  • • Change in scope of work
  • • Delay in project

• Contractor has to investigate site conditions prior to starting the relevant activity.

1.3

Inadequate site investigation data

  • • Additional work
  • • Scope change

• Contractor has to investigate site conditions prior to starting the relevant activity.

1.4

Conflict in contract documents

• Project delay

• Amicably resolve the issue.

1.5

Incomplete design

  • • Project scope
  • • Project schedule
  • • Project cost
  • • Raise request for information (RFI).
  • • Resolve issue in accordance with ontract documents

1.6

Incomplete scope of work

  • • Project scope
  • • Project schedule
  • • Project cost
  • • Raise RFI.
  • • Resolve issue in accordance with contract documents.

1.7

Design changes

  • • Project scope
  • • Project schedule
  • • Project cost

• Follow contract documents for change order.

1.8

Design mistakes

  • • Project scope
  • • Project schedule
  • • Project cost
  • • Raise RFI.
  • • Resolve issue in accordance with contract documents.

1.9

Errors and omissions in contract documents

  • • Project scope
  • • Project schedule
  • • Project cost
  • • Raise RFI.
  • • Resolve issue in accordance with contract documents.

TABLE 1.15 (Continued)

Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action

Sr. No.

Potential Risk

Probable Effects

Control Measures/Mitigation Action

1.10

Incomplete

specifications

  • • Project scope
  • • Project schedule
  • • Project cost
  • • Raise RFI.
  • • Resolve issue in accordance with contract documents.

1.11

Conflict with different trades

• Project delay

• Coordinate with all trades while preparing coordination and composite drawings.

1.12

Inappropriate construction method

  • • Project delay
  • • Claim

• Raise RFI and correct the method statement.

1.13

Quality of material

• Project delay

• Locate suppliers having proven record of supplying quality product.

2.0 Schedule

2.1

Incompetent

subcontractor

  • • Project delay
  • • Project quality

• Contractor has to monitor the workmanship and work progress.

2.2

Delay in transfer of site

• Project delay

• Contractor has to adjust the construction schedule.

2.3

Delay in mobilization

• Project delay

• Adjust construction schedule accordingly.

2.4

Project schedule

• Project completion

• Compress duration of activities.

2.5

Inappropriate

schedule/plan

• Project delay

• Contractor has to prepare schedule taking into consideration site conditions all the required parameters.

2.6

Delay in change order negotiations

• Project schedule

• Request owner/supervisor/project manager to expedite the negotiations and resolve the issue.

2.7

Resource availability (material)

• Project delay

• Contractor has to make extensive search.

2.8

Resource (labor) low productivity

  • • Project quality
  • • Project delay

• Contractor has to engage competent and skilled labors.

2.9

Equipment/plant

productivity

• Project delay

• Contractor has to hire/purchase equipment to meet project productivity requirements.

2.10

Insufficient skilled workforce

• Project duration

• Contractor has to arrange workforce from alternate sources.

1.11

Failure/delay of machinery and equipment

• Project delay

• Contractor has to plan procurement well in advance.

1.12

Failure/delay of material delivery

• Project delay

• Contractor has to plan procurement well in advance.

2.13

Delay in approval of submittals

• Project delay

• Notify owner/project manager.

2.14

Delays in payment

  • • Project delay
  • • Claim
  • • Contractor has to have contingency plans.
  • • Owner has to pay as per contract.

TABLE 1.15 (Continued)

Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action

Sr. No.

Potential Risk

Probable Effects

Control Measures/Mitigation Action

2.15

Statutory/regulatory

delay

• Project delay

• Regular follow-up by the contractor and owner with the regulatory agency.

3.0 Cost

3.1

Low bid project cost

• Project quality

• Contractor has to try competitive material and improve method statement and higher production rate from its manpower.

3.2

Variation in construction material price

  • • Project quality
  • • Project cost

• Contractor has to negotiate with supplier/ manufacturer for best price. Contractor has to request for change order if applicable as per contract.

3.3

Damage to equipment

• Schedule

• Regularly maintain the equipment. Take immediate action to repair damage equipment.

3.4

Damage to stored material

  • • Project delay
  • • Material quality

• Contractor has to follow proper storage system.

3.5

Structure collapse

  • • Injuries
  • • Project delays

• Contractor has to ensure that formwork and scaffolding is properly installed.

3.6

Leakage of hazardous material

• Safety Hazards

• Contractor has to take necessary' protect to avoid leakage. Store in safe area.

4.0 General

4.1

Failure of team members not performing as expected

  • • Project quality
  • • Project delay

• Select competent candidate. Provide training.

4.2

Change in laws and regulations

  • • Scope/specification changes
  • • Variation order

• Contractor has to inform owner/consultant and raise RFI.

4.3

Access to worksite

• Extra/additional time to access site

• Access road to be planned in coordination with adjacent area and local authority.

4.4

Theft at site

• Project delay

• Contractor has to monitor access to site. Record entry/exit to the site. Provide fencing around project site.

4.5

Fire at site

• Project delay

• Contractor has to install temporary firefighting system. Inflammable material should be stored in safe and secured place with necessary' safety measures.

4.6

Injuries

• Project delay

• Contractor has to keep first aid provision at site. Take immediate action to provide medical aid.

TABLE 1.15 (Continued)

Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action

Sr. No.

Potential Risk

Probable Effects

Control Measures/Mitigation Action

4.7

New technology

  • • Scope change
  • • Schedule
  • • Cost

• Owner/contractor has to mutually agree for changes in the contract for better performance of project.t

Source: Abdul Razzak Rumane. (20I6). Handbook of Construction Management: Scope, Schedule, and Cost Control. Reprinted with permission from Taylor & Francis Group.

all supply chain-related activities at all the levels of product/project life cycle to ensure competitiveness of end product. It is a process to ensure that the customer gets right product or service having right quality and quantity on time.

Supply chain management is very complex process which has involvement of many participants both within and outside the organization. Each of these participants has influence over the activities to be performed to ensure availability of the product for further processing.

 
Source
< Prev   CONTENTS   Source   Next >