Supply Chain Management
Supply chain management is a new concept of doing business, which has been recognized and practiced by the manufacturing industry for the last two decades. It has also emerged as new practice in construction industry.
Because of emerging technological advances and to maintain competitive advantage in business environment, it has become essential to plan, organize, and control
TABLE 1.14
Typical Categories of Risks in Oil and Gas Projects
Sr. No. |
Category |
Types |
1 |
Management |
Selection of project delivery and contracting system Selection of project management consultant |
2 |
Contract (project) |
Scope/design changes Schedule Cost Conflict resolution Delay in changer order negotiations |
3 |
Statutory |
Statutory/regulatory delay |
4 |
Technical |
Incomplete design Incomplete scope of work Design changes Design mistakes Errors and omissions in contract documents Incomplete specifications Ambiguity in contract documents Inconsistency in contract documents Inappropriate schedule/plan Inappropriate construction method Conflict with different trades Improper coordination with regulatory authorities Inadequate site investigation data |
5 |
Technology |
New technology |
6 |
Construction |
Delay in mobilization Delay in transfer of site Different site conditions to the information provided Changes in scope of work Resource (labor) low productivity Equipment/plant productivity Insufficient skilled workforce Union and labor unrest Failure/delay of machinery and equipment Quality of material Failure/delay of material delivery Delay in approval of submittals Extensive subcontracting Subcontractor’s subcontractor Failure of project team members to perform as expected Information flow breaks |
TABLE 1.14 (Continued)
Typical Categories of Risks in Oil and Gas Projects
Sr. No. |
Category |
Types |
7 |
Physical |
Damage to equipment Structure collapse Damage to stored material Leakage of hazardous material Theft at site Fire at site |
8 |
Logistic |
Resources availability Spare parts availability Consistent fuel supply Transportation facility Access to worksite Unfamiliarity with local conditions |
9 |
Health, safety, and environment |
Injuries Health and safety rules Environmental protection rules Pollution rules Disposal of waste |
10 |
Financial |
Inflation Recession Fluctuations in exchange rate Availability of foreign exchange (certain countries) Availability of funds Delays in payment Local taxes |
11 |
Economical |
Variation of construction material price Sanctions |
12 |
Commercial |
Import restrictions Custom duties |
13 |
Legal |
Permits and licenses Professional liability Litigation |
14 |
Political |
Change in laws and regulations Constraints on employment of expatriate workforce Use of local agent and firms Civil unrest War |
15 |
Natural/environmental |
Flood Earthquake Cyclone Sandstorm Landslide Heavy rains High humidity Fire |
TABLE 1.14 (Continued)
Typical Categories of Risks in Oil and Gas Projects
Sr. No. |
Category |
Types |
16 |
Geological |
Estimation of accessible reserves |
17 |
Supply and demand |
Financial crises and macroeconomic factors |
18 |
Operational |
Availability of skilled workers |
EPC, engineering, procurement, and construction.
Source: Abdul Razzak Rumane. (2013). Quality Tools for Managing Construction Projects. Reprinted with permission from Taylor & Francis Group.
TABLE 1.15
Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action
Sr. No. |
Potential Risk |
Probable Effects |
Control Measures/Mitigation Action |
1.0 Scope |
|||
l.l |
Scope/design changes |
|
|
1.2 |
Different site conditions to the information provided |
|
• Contractor has to investigate site conditions prior to starting the relevant activity. |
1.3 |
Inadequate site investigation data |
|
• Contractor has to investigate site conditions prior to starting the relevant activity. |
1.4 |
Conflict in contract documents |
• Project delay |
• Amicably resolve the issue. |
1.5 |
Incomplete design |
|
|
1.6 |
Incomplete scope of work |
|
|
1.7 |
Design changes |
|
• Follow contract documents for change order. |
1.8 |
Design mistakes |
|
|
1.9 |
Errors and omissions in contract documents |
|
|
TABLE 1.15 (Continued)
Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action
Sr. No. |
Potential Risk |
Probable Effects |
Control Measures/Mitigation Action |
1.10 |
Incomplete specifications |
|
|
1.11 |
Conflict with different trades |
• Project delay |
• Coordinate with all trades while preparing coordination and composite drawings. |
1.12 |
Inappropriate construction method |
|
• Raise RFI and correct the method statement. |
1.13 |
Quality of material |
• Project delay |
• Locate suppliers having proven record of supplying quality product. |
2.0 Schedule |
|||
2.1 |
Incompetent subcontractor |
|
• Contractor has to monitor the workmanship and work progress. |
2.2 |
Delay in transfer of site |
• Project delay |
• Contractor has to adjust the construction schedule. |
2.3 |
Delay in mobilization |
• Project delay |
• Adjust construction schedule accordingly. |
2.4 |
Project schedule |
• Project completion |
• Compress duration of activities. |
2.5 |
Inappropriate schedule/plan |
• Project delay |
• Contractor has to prepare schedule taking into consideration site conditions all the required parameters. |
2.6 |
Delay in change order negotiations |
• Project schedule |
• Request owner/supervisor/project manager to expedite the negotiations and resolve the issue. |
2.7 |
Resource availability (material) |
• Project delay |
• Contractor has to make extensive search. |
2.8 |
Resource (labor) low productivity |
|
• Contractor has to engage competent and skilled labors. |
2.9 |
Equipment/plant productivity |
• Project delay |
• Contractor has to hire/purchase equipment to meet project productivity requirements. |
2.10 |
Insufficient skilled workforce |
• Project duration |
• Contractor has to arrange workforce from alternate sources. |
1.11 |
Failure/delay of machinery and equipment |
• Project delay |
• Contractor has to plan procurement well in advance. |
1.12 |
Failure/delay of material delivery |
• Project delay |
• Contractor has to plan procurement well in advance. |
2.13 |
Delay in approval of submittals |
• Project delay |
• Notify owner/project manager. |
2.14 |
Delays in payment |
|
|
TABLE 1.15 (Continued)
Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action
Sr. No. |
Potential Risk |
Probable Effects |
Control Measures/Mitigation Action |
2.15 |
Statutory/regulatory delay |
• Project delay |
• Regular follow-up by the contractor and owner with the regulatory agency. |
3.0 Cost |
|||
3.1 |
Low bid project cost |
• Project quality |
• Contractor has to try competitive material and improve method statement and higher production rate from its manpower. |
3.2 |
Variation in construction material price |
|
• Contractor has to negotiate with supplier/ manufacturer for best price. Contractor has to request for change order if applicable as per contract. |
3.3 |
Damage to equipment |
• Schedule |
• Regularly maintain the equipment. Take immediate action to repair damage equipment. |
3.4 |
Damage to stored material |
|
• Contractor has to follow proper storage system. |
3.5 |
Structure collapse |
|
• Contractor has to ensure that formwork and scaffolding is properly installed. |
3.6 |
Leakage of hazardous material |
• Safety Hazards |
• Contractor has to take necessary' protect to avoid leakage. Store in safe area. |
4.0 General |
|||
4.1 |
Failure of team members not performing as expected |
|
• Select competent candidate. Provide training. |
4.2 |
Change in laws and regulations |
|
• Contractor has to inform owner/consultant and raise RFI. |
4.3 |
Access to worksite |
• Extra/additional time to access site |
• Access road to be planned in coordination with adjacent area and local authority. |
4.4 |
Theft at site |
• Project delay |
• Contractor has to monitor access to site. Record entry/exit to the site. Provide fencing around project site. |
4.5 |
Fire at site |
• Project delay |
• Contractor has to install temporary firefighting system. Inflammable material should be stored in safe and secured place with necessary' safety measures. |
4.6 |
Injuries |
• Project delay |
• Contractor has to keep first aid provision at site. Take immediate action to provide medical aid. |
TABLE 1.15 (Continued)
Potential Risks on Scope, Schedule, and Cost during Construction Phase and Its Effects and Mitigation Action
Sr. No. |
Potential Risk |
Probable Effects |
Control Measures/Mitigation Action |
4.7 |
New technology |
|
• Owner/contractor has to mutually agree for changes in the contract for better performance of project.t |
Source: Abdul Razzak Rumane. (20I6). Handbook of Construction Management: Scope, Schedule, and Cost Control. Reprinted with permission from Taylor & Francis Group.
all supply chain-related activities at all the levels of product/project life cycle to ensure competitiveness of end product. It is a process to ensure that the customer gets right product or service having right quality and quantity on time.
Supply chain management is very complex process which has involvement of many participants both within and outside the organization. Each of these participants has influence over the activities to be performed to ensure availability of the product for further processing.